Repair Facilities Damaged by Typhoon Mawar at USCG Sector Guam
Client: USDHS / USCG
Prime Contractor: Tridon Corporation
Project Amount: $2,266,734.88
Contract Role: Subcontractor
Contract Amount: Time and Material Contract
Project Duration: March 2024 to December 2024
Project Location: USCG Sector Guam
Scope of Work:
Complete renovation of Chief’s Mess Hall and be converted to a new HSWL workshop, renovation includes:
- Complete replacement of floor and walls including structural support and framing.
- Complete replacement of windows and doors including typhoon shutters.
- Installation of new floor and wall finishes.
- Construction of ADA Ramp, railing and canopy.
Aplacho Drainage and Roadway Improvements
Client: Guam Waterworks Authority (GWA)
Prime Contractor: A&R Pacific
Project Amount: $ 1,053,819.91
Contract Role: Subcontractor
Contract Amount: $ 210,030.56
Project Duration: January 2025 to April 2025
Project Location: Cross Island Road, Sta. Rita, Guam
Scope of Work:
- Asphalt Concrete Roadway Removal and Restoration
- Construction of Subterranean Drainage across the road to divert stormwater to the headwall
- Construction of two (2) New Concrete Headwall
- Construction of Guardrail
- Turf Establishment
GWA EMERGENCY GAC VESSEL RELOCATION & INSTALLATION
Client: Guam Waterworks Authority (GWA)
Prime Contractor: A&R Pacific
Project Amount: TBD
Contract Role: Subcontractor
Contract Amount: Time and Material Contract
Project Duration: September 19, 2025 to October 14, 2025
Project Location: Dededo & Yigo Guam
Scope of Work:
- Rehabilitation of Existing Tank, including Cleaning, Painting and installation of Support Anchor
- Relocation of Existing tank to New Location
- Construction of Concrete Pad
- Installation of Pipes and Fittings
- Hydro Static and Leak Test